AQO 1861/17-22 Oral question to the Minister for Communities

To ask the Minister for Communities what discussions she has had with the Housing Executive on proposed delays to the action plan on any significant work to correct cavity wall insulation.

Asked by Kellie Armstrong MLA on 18 March 2021

  • Answered
  • Oral
  • After due date
Tabled
18 March 2021
Answer due by
13 April 2021
Answered
19 April 202132 days after tabling
Department
Department for Communities
Priority question
No

Answer

I have spoken many times about the significant backlog the Housing Executive faces in stock investment and the £7.8 billion deficit in its funding.

The Housing Executive published its draft Cavity Wall Insulation Action Plan for consultation in December. That consultation has just closed and the responses received will be carefully considered before the final plan is published later this year.

Once it has the funding to do so the Housing Executive intends to implement a cavity wall insulation remediation/replacement programme which will be an integral part of its Energy Efficiency Strategy. Not only will this strategy help address fuel poverty and improve tenants’ comfort, it will play a major part in the Housing Executive’s effort to contribute to decarbonisation