AQW 30682/17-22 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure why the Strangford Ferry was pulled out of operation at short notice on 4 March 2022.

Asked by Kellie Armstrong MLA on 8 March 2022

  • Answered
  • Written
Tabled
8 March 2022
Answer due by
24 March 2022
Answered
24 March 202216 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

The Maritime and Coastguard Agency (MCA) approved Safety Management System for the Strangford Ferry requires a minimum crew of four to be on board to sail. On Friday 4 March 2022 at approximately 7.30pm, a situation arose where there were insufficient crew members available for the next scheduled sailing so the ferry had to be taken out of service. Normal service resumed on Saturday morning, 5 March.

Managing essential services during the pandemic continues to present challenges, however please be assured that the whole ferry team are working hard to keep this important transport link operational.