AQW 29764/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to detail the compensation costs incurred following the decision on the A5 Western Transport Corridor scheme.
Asked by Kellie Armstrong MLA on 2 July 2025
- Answered
- Written
- Tabled
- 2 July 2025
- Answer due by
- 21 July 2025
- Answered
- 10 July 20258 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
The judge quashed the decision and the orders, taking effect from the 27 June 2025. To date there have been no compensation costs incurred.