AQW 36238/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to provide a copy of the evaluation or rationale, explaining why the proposal to replace the Strangford Ferry with a bridge, was not previously considered.
Asked by Kellie Armstrong MLA on 25 November 2025
- Answered
- Written
- Tabled
- 25 November 2025
- Answer due by
- 10 December 2025
- Answered
- 10 December 202515 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
The 2013 Strategic Review of the Strangford Lough Ferry Service considered alternative proposals to the ferry service, including the option of a bridge however, the review concluded a bridge was not an economically viable solution. The subsequent business case for the replacement of MV Strangford did not consider the provision of a bridge given that its central objective was to enable the Strangford Lough Ferry Service to continue to operate the current scheduled service.
The Strangford Lough Ferry Service operates every day of the year except Christmas day, from early morning to late-night serving both the local community and local tourism through the provision of a reliable service and is considered the most economical transportation link between Strangford and Portaferry.