AQW 23033/17-22 Written question to the Minister of Education
To ask the Minister of Education (i) for an update on the progress of the Fresh Start support funding for Integrated Education for potential new buildings or refurbishments; (ii) to confirm the position in the process for each school accepted for a new build; and (ii) when each build is expected to break ground.
Asked by Kellie Armstrong MLA on 23 September 2021
- Answered
- Written
- Tabled
- 23 September 2021
- Answer due by
- 8 October 2021
- Answered
- 5 October 202112 days after tabling
- Department
- Department of Education
- Priority question
- No
Answer
The Fresh Start Agreement (FSA) set out a commitment by the UK Government (UKG) to release up to £500m of new capital funding over 10 years to support shared and integrated education and housing, subject to individual projects being agreed between the Executive and the UKG. The Fresh Start announcement in 2016 confirmed funding for 17 schemes to proceed to planning and approval for construction in 6 projects. In June 2018, the Secretary of State for Northern Ireland announced approval to release FSA funding for the Strule SEC Programme. A further announcement in November 2018 confirmed funding for a further 5 integrated schemes to proceed in principle. A full list of projects is included in the table below, which indicates the current position and the anticipated start on site.
The total spend from the Fresh Start allocation to the end of the financial year 2020/21 is just under £37.3m. While this spend to date is low relative to the overall £500m total available, this is to be expected in a programme of this size where the early work on procuring design teams, identifying site options, preparing business cases, completing the design and procuring a contractor is very time-consuming but not capital intensive. The projected spend profile will ramp up significantly in coming years as projects move into the construction phase.
The following table indicates the current status and anticipated start date of the 28 projects (excluding Strule) announced to date. Capital Projects are complex by their very nature and a variety of factors can contribute to delays which cumulatively impact on delivery of a project. The programme will of course be subject to regular review, particularly in light of the ongoing Covid-19 situation.
| Projects Completed | Anticipated on Site |
| Drumlins Integrated Primary School | Completed September 2017 |
| Braidside Integrated Primary School | Completed July 2020 |
| Contractor Appointed | |
| Limavady Shared Education Campus (Limavady High School & St Mary’s Limavady) | Started on site March 2021 |
| Enniskillen Integrated Primary School | Started on site June 2021 |
| Roe Valley Integrated Primary School | Anticipated start date late 2021 |
| Ulidia Integrated College | Anticipated start date early 2022 |
| Contractor expected to be appointed in the current Financial Year 2021-22 | |
| Strangford Integrated College | Anticipated start summer 2022 |
| Rowandale Integrated Primary School | Anticipated start summer 2022 |
| Shimna Integrated College | Anticipated start late spring 2022 |
| Millennium Integrated Primary School | Anticipated start summer 2022 |
| Phoenix Integrated Primary School | Anticipated start spring 2022 |
| Ballycastle Shared Education Campus (Ballycastle High School & Cross and Passion College) | Anticipated start summer 2022 |
| New-Bridge Integrated College | Anticipated start late spring 2022 |
| Projects in the later stages of design | |
| Mill Strand Integrated Primary School | Anticipated start winter 2022 |
| Forge Integrated Primary School | Anticipated start winter 2022 |
| Priory College | Anticipated start spring 2023 |
| Bangor Central Integrated Primary School | Anticipated start spring 2023 |
| Projects in the early design stages | |
| Moy Shared Education Campus (Moy Regional PS & St John’s PS) | Anticipated start winter 2023 |
| Fort Hill College | Anticipated start spring 2024 |
| Fort Hill Integrated Primary School | Anticipated start spring 2024 |
| Hazelwood Integrated College | Anticipated start spring 2024 |
| Slemish Integrated College | Anticipated start winter 2023 |
| Integrated College Dungannon | Anticipated start winter 2023 |
| Parkhall Integrated College | Anticipated start winter 2022 |
| Drumragh Integrated College | Anticipated start spring 2023 |
| Brookeborough Shared Education Campus (St Mary’s PS & Brookeborough PS) | Anticipated start spring 2024 |
| Projects on hold or withdrawn. | |
| North Coast Integrated College | N/A |
| Duneane / Moneynick Shared Education Campus | N/A |